Project Timeline
A timeline of the project is as follows:
- Boller Construction selected to complete Phase II | April 2025 |
- Phase II Request for Proposals | February 2025 |
- Presentation of Phase II 90% Complete Plan | January 2025 |
- Presentation of Phase II 50% Complete Plan | November 2024 |
- Phase I was completed | October 2024 |
- The design contract for Phase II, The Library’s Great Lawn, was signed with Hitchcock Design Group | September 2024 |
- LVDL awarded Open Space Land Acquisition & Development Grant | January 2024 |
- Contract signed with Joseph J. Henderson & Son | January 2024 |
- Request for proposals | November 2024 |
- Phase I Project selected - Library Garden | September 2023 |
- Presentation of 95% Complete Plan | March 2023 |
- Presentation of 50% Complete Plan | November 2022 |
- Community survey & focus groups | May 2022 |
- Contract signed with Hitchcock Design Group | January 2022 |
- Interviewed the top three firms | December 2021 |
- Request for Qualifications for Landscape Architects | October 2021 |